31st May and 7th June 2026 – Report and Photographs by Oliver Mills

The Committee of the National Piers Society was delighted to be invited to inspect the works at the Birnbeck Pier site, with a tour led by Rachel Lewis, Heritage and Design Manager of North Somerset Council. On this day, the 31st May, the first replacement span was still being assembled in the foreshore compound (more regarding it will be revealed later). In the photograph ABOVE, taken upon my arrival in Weston at 12:30, the pier is shown with the bridge superstructure entirely stripped (except for the outermost span, No.1 (No.16 at the shoreward end)), with the jack-up rig installed beside Span No.15, and reconstruction works at an advanced stage at the landside buildings.
Anyway, prior to other members arriving, I inspected the pier’s condition from afar:
ABOVE LEFT: The full scale of the construction plant in-situ on the construction site, visible throughout much of Weston-Super-Mare.
ABOVE RIGHT: view into the substructure of the pier bridge, with the removal of the superstructure (decking) revealing much of the bracing between the girders for the first time. New temporary ties have been installed to prevent movement between the two parallel girder lines. Regardless, the girders’ visible deflection from the true line, emphasised in this foreshortened view, is quite startling. Much of this may be the result of the buckling of the girder lattices through deterioration.
ABOVE LEFT: Detail of the South girder line on Span No.12, not exactly “buckled”, but rather “disintegrated”. There is almost total loss of the bottom connection of the lattice chords; resultantly, the top flange appears to be sagging slightly. Note also the near-total loss of the transverse deck support beam’s web (top-right). The North Jetty, of course, is a famous example of girder web/lattice loss drawn to its most ruinous extreme, pictured ABOVE RIGHT.
ABOVE: Views of the construction compound perimeter, planned to maintain public access around much of the promenade. Visible RIGHT are the ongoing works to lay new electricity mains to the site, which naturally requires entirely new services of almost every percievable kind.
At 13:00 the tour began, with a party including NPS Committee members Tim Wardley, Caroline Buttolph, Neil Thomas-childs and myself, as well as members of the MV Balmoral charity.

ABOVE: The most critical sign of progress, present at the site at the time of the visit: the replacement steelwork for Span No.16. Unlike the original riveted lattice girders, this replacement is formed from solid-webbed plate girders of steel, with the webs pierced to imitate a lattice girder, and then strengthened with welded stiffeners. There are also lateral braces under the deck level, and visible topmost are the transverse deck support beams. Just about visible beneath are the reinforced plastic mesh trays, to carry the services under-deck.
ABOVE LEFT: The iron ruins of Span No.16, deposited in the landside compound, including a vivid example of how new even the most wrecked ironwork can look when freshly cut. Elsewhere, however, the ironwork had reduced to razer-sharp shreds of oxide.
ABOVE RIGHT: A view along the length of the pier, from the landside abutment. The new concrete structure in the foreground will act as the abutment itself, carrying the bearings that the Span No.16 steelwork will rest on. This abutment is actually a deceptively substantial structure; it is L-shaped in cross-section and the steel will rest on the (unseen) flat flange of the opposite side. The topmost surface will ultimately represent the finished deck level, covered over with steel capping, and the rectangular aperture is devoted to the under-deck services. The whole structure is to be 1.6m deep, but only 300mm is visible from this angle.
ABOVE LEFT: New steelwork, to be installed as bracing for Tower No.15 (given away by the steel collar in the background, to be clamped around each of the existing iron columns).
ABOVE RIGHT: A general view towards the works surrounding Tower No.15. The red-coloured scaffolding platforms serve as working platforms for restoring the tower itself; this foremost will involve the removal of old ruined bracing and the installation of their replacements. The original 1867 spider bracing will be replaced, with the retrofitted 1912 lattice bracing above and below it also being reinstated in the form of Parallel Flange Channel members, as shown LEFT.
Later in the afternoon, the inspection of the pier continued with a cruise on the P.S. Waverley. This berthed at the nearby Knightstone Island, overlooking the Grand Pier, and naturally drew considerable crowds.




ABOVE: Sequential views of Birnbeck Island, starting on the South side and continuing to the rather more rarely-seen North side. Finally, a detail view of the landing stage of the North Jetty, which naturally will be entirely replaced with a new structure intended on accepting berthings from such pleasure ships as the Waverley and Balmoral.
ABOVE LEFT: Tim Wardley, NPS Chairman and Piers & Harbours Liaison Officer of Waverley Excursions, with Waverley colleagues on the deck.
ABOVE RIGHT: A restful scene from Waverley’s upper deck, having just departed Penarth Pier.
ABOVE AND BELOW: Arrival at Clevedon Pier, the terminus of the cruise, and truly magical in its lighting quality at this time of the evening.

And then there is more! I revisited Weston-Super-Mare on my return journey from Devon (Teignmouth, Paignton and Torquay Piers will be reported on next week), on Sunday 7th June. Striking progress had been underway, and although there were suggestions that the first steelwork would be craned into position on Friday, it ended up being initiated on Sunday, only an hour or so prior to me arriving.

ABOVE: looking down towards Tower No.15 and Span No.16, with the previously-seen steelwork now being craned in position. On the jack-up barge is, with some colleagues, Rachel Lewis who we met only a week before
ABOVE LEFT: A view from the lower promenade, showing the new steel of Span No.16 against the old. At this point, it was still in suspension and had not yet been lowered directly to the pile caps. Verification from the project leaders and engineers to do so was given some 30 minutes later.
ABOVE RIGHT: A detail view of the span interfaces over Tower No.15; it can be seen that the new steel is still slightly raised relative to the old iron span. Also apparent on the new steel are the transverse deck support beams, each topped with a board of Ekki hardwood (to act as a plate for the decking planks, laid above it in longitudinal orientation, to be bolted to). The white-painted components are the seat supports.
ABOVE LEFT: A detail view of Tower No.15, showing parts of the new steel bracing (the black-painted steel) installed. Just about visible, level with the lower scaffolding floor, are the collars for the replaced spider bracing.
ABOVE RIGHT: The engineers in the basket, inspecting the cast iron columns of Tower No.13 (“Oh, the posh, posh travelling life, the travelling life for me”).

ABOVE, AND FINALLY: A photograph taken slightly later, at 14:30, confirming the steelwork for Span No.16 to be down and solidly in place. Thusly, it now serves as a working platform for decking works to commence. Shown here are the craning and fixing of two final transverse deck support beams. This was necessary in the aftermath since their respective fixing holes were previously used to carry the entire span into position. At the time of writing (11/06/26, 21:52… the precision being necessary since things are advancing so rapidly!), there have been reports that the laying of the principal decking is already underway, with the Ekki decking boards being laid at right angles over those shown above.
In short, excellent, miraculous work from North Somerset Council, their partners, and the Birnbeck Regeneration Trust! This work will continue to court frenzied fascination from all types: locals, visitors, engineers and even those who never realised that seaside piers could be so exciting. It is presently anticipated that these people will be walking across the pier bridge ONE YEAR FROM NOW.